October 15, 2026
On December 1, Three Rivers Park District will close about two miles of the Dakota Rail Regional Trail in Orono, from North Shore Drive to Orono Orchard Road. The trail stays closed through March 31, and Three Rivers will not post a detour. Three Rivers lists Orono among the communities where the trail is plowed in winter.
The trail closure lasts four months. The work causing it runs much longer. Metropolitan Council Environmental Services is laying a new regional sewer pipe from a lift station on Lilac Lane to Orono Orchard Road. The trail is just the last leg of the route, and the streets before it will be dug up in sequence until 2028.
The Dakota Rail corridor west of Wayzata has three separate closures this fall and winter.
| Closure | Segment | Window | Cause |
|---|---|---|---|
| Orono | North Shore Drive to Orono Orchard Road, about 2 miles | December 1 through March 31 | Met Council sewer line installation |
| Mound and Minnetrista | Shoreline Drive in Mound to Westonka Recreation Park, about 2.5 miles | October 15 through end of February | Xcel Energy transmission line replacement |
| Mound crossing | Trail at Commerce Boulevard | Beginning October 5 | Hennepin County road project, ADA ramp upgrades |
Three Rivers' trail page says the trail remains open between the two long closures. Only the Commerce Boulevard crossing in Mound has a posted detour. The page links closure maps for both segments, labeled for fall and winter 2026–27. Check the Orono map before you plan a loop that depends on a particular access point.
The Met Council calls the project Orono Sewer Improvements, Project 802897. The construction contract is listed as Orono Interceptor 7113 Improvements, Contract 25P335. The project page describes the route in this order:
The project won't replace the existing pipe. Met Council committee documents describe a new, full-length redundant forcemain, with interconnection structures and new meters, built beside the existing 7113 forcemain. That line went in in 1979 and serves L59. The Council lists aging infrastructure, pipe condition, current flow volume and operational flexibility as the reasons for the project.
The 1979 line has a known history. In February 2024, the City of Orono posted a notice that a Met Council condition assessment had found significant corrosion between French Creek Drive and Railroad Avenue. Repairs followed along North Shore Drive between Pine Lane and Shoreline Drive. Today's project builds a second pipe, so the system no longer rests on that one aging forcemain.
The existing pipe and the new one share a path at first and then split. The project map shows the old line heading east to Shoreline Drive and then northeast along it. The new line turns off onto the Dakota Rail corridor. That turn is the reason the trail is part of this at all.
A May 2026 item before the Council's Environment Committee proposed awarding the contract to Meyer Contracting Inc. for up to $25,657,165.46. The project page, updated August 20, 2026, said bids had come in and contractor negotiations had begun.
Three Rivers explains the timing in one sentence on its trail page: "Use of the trail decreases significantly during the winter months, and these projects were scheduled during fall and winter to minimize disruption to trail use."
The trail closure has a fixed four-month window. The street work on the rest of the route is scheduled in years.
The trail also gets a better surface out of this. Three Rivers says sections of trail affected by the sewer construction will be repaved as part of the project.
On Old Crystal Bay Road, North Shore Drive and Brown Road, the schedule is set in years. The Met Council says it will use both open-trench and trenchless tunneled methods, and it will work one street at a time. The agency says this approach can make the project take longer, and it chose it anyway to avoid wider neighborhood disruption.
The project page expects construction to start in late 2026 and finish in spring or summer 2028. The Council's contract schedule goes a little further. It lists fall 2026 for the start, summer 2028 for substantial completion and fall 2028 for final completion. So plan on some activity somewhere along the route for close to two years, and on restoration work that may run into the second half of 2028.
According to the project page, here's what work on a given street involves:
The Met Council held an in-person pre-construction meeting on Thursday, September 24, at the Minnetonka Center for the Arts, 2240 North Shore Drive. The project page offers email and text updates for anyone who missed it, and that's the most direct way to find out which street is next.
The trail outside the closed segments stays open. Three Rivers lists the plowed sections in Orono, Spring Park, Wayzata, Minnetonka Beach and part of Mound. Its listed access points include the Navarre municipal parking lot at 3401–3465 Lyric Avenue, 175 Grove Lane in Wayzata and 5515 Lynwood Boulevard in Mound. Compare the Orono closure map with your usual starting point. Depending on where you park, a loop might just get shorter instead of disappearing.
The Shoreline Drive stretch through Navarre and Spring Park still works as a place to stop. These places had current hours posted when we checked this fall:
Across the road, Minnetonka Drive In at 4658 Shoreline Drive says on its site that it is closed for the 2026 season.
For anyone who wants a full winter route, three alternatives are within a short drive:
Luce Line State Trail. This 63-mile former rail grade has a Long Lake access by Old Crystal Bay Road. The DNR's Luce Line page points hikers, skiers and winter bikers to the segment between Vicksburg Lane and Stubbs Bay Road. The page's trail alert was last updated October 9, 2026. Old Crystal Bay Road is also on the sewer route, so check which street the crews are on before you drive to that access.
Baker Park Reserve. At 2309 County Road 19 in Maple Plain, Baker Park has 9.1 miles of groomed classic and skate-ski trails. When conditions allow, you can reserve equipment online up to seven days ahead and pick it up at the Baker Winter Trailhead. Three Rivers says to check winter rates in early November.
Gale Woods Farm. At 7210 County Road 110 W. in Minnetrista, Gale Woods has 4.2 miles of ungroomed snowshoe trails. Rentals can be reserved up to seven days ahead, and as late as two hours before you go when there's enough snow. The farm sits next to the Xcel closure on the Dakota Rail, which runs past Gale Woods until the end of February, so drive there instead of riding the trail.
The Orono trail closure is scheduled to end March 31. Three Rivers says the affected sections will be repaved as part of the project, but it hasn't published a date for the repaving. The sewer work doesn't end in spring either. The Met Council's schedule lists substantial completion in summer 2028 and final completion in fall 2028. The project page carries the current schedule, and that's where repaving and street dates will show up as they're set.
If your home is on Old Crystal Bay Road, North Shore Drive, Brown Road or near the trail, the construction calendar can affect the timing of a sale, from listing photos to showings and when buyers can actually drive to the house. Michelle & Patrick Homes tracks projects like this one block by block. Request your home valuation and we'll walk you through how the 2026–2028 schedule lines up with your plans.